No Image Found   

Failed List Report

Chas Municipal Corporation

Version Number: 1.0.59  
Version Date: 16/10/2020 
Report Generated On: 24-07-2021 
 

[-] Collapse All


General Details
RegionJHARKHAND URBAN LOCAL BODIES
DistrictBOKARO
AuthorityCHAS MUNICIPAL CORPORATION
Inward_NoCMC/BP/0105/W19/2021
Application TypeGeneral Proposal
Project TypeBuilding Permission
Nature of DevelopmentNew
Location of Development AreaOld Area
City Area/TPScheme NoNA
VillageChas
Taluka17
Architect Details
Architect NameSuresh Prasad Singh
License No.CMC/ENG/0002/2017
Architect Address414, Sector III D,Steel City Bokaro
Architect EmailIDsinghsp.2014@rediffmail.com
Architect Mobile No7970758220
Plot Details
Plot Use Mixed
Plot SubUse Resi+Comm
PlotNearbyReligiousStructure NA
Plot/SubPlot No7703,7704,7705
NorthRoad Width - 21
SouthCTS No. - KEJRIWAL LAND
EastCTS No. - ASHOK & VIJAY KUMAR KEDIA
WestCTS No. - MAHTO MARKET
Owner's Details
Name(1) JULLY DEVI KEDIA (2)RAJESH KUMAR KEDIA
AddressOPPOSITE KEDIA BHAWAN, NEAR BIHAR COLONY, MAIN ROAD CHAS
Email IDmuva.rajesh@gmail.com
Mobile No9431128104
[-] Plot Details (Table 2)

[-] Area From Document (Table 2a)
No. Form Area
1 Deed(Sale Deed, Gift Deed and Lease Deed) or Agreement 457.87
2 Plot area as per Document by Applicant 457.87
3 Physical area measured at site 457.87
4 Area as per Site Visit (Site Visit Report) 457.87
5Area as per Drawing 457.87

Area of Plot Considered : 457.87

[-] Table 2b
Proposal Detail :
UnitMeters
Development Detail :
PlotPLOT
Plot OccupancyMixed
Plot SubUse -
Higher Plot Use
Higher Plot Sub UseResi+Comm
Lower Plot Use
Lower Plot Sub Use
Building StructureMultistoried
Building TypeSingle Detached House
Gross Plot Area 457.87
Net Plot Area (Gross Plot Area - Deduction from Gross Plot area) 457.87
Balance Plot Area (Net Plot Area - Recreational/Amenity space) 411.76
Deductions for Balance Plot Area (from Gross Plot Area)
- Common Plot 46.11
46.11
Balance Plot Area 411.76

[-] Table 2c
COVERAGE CHECK
Permissible Coverage area ( 60.00 % ) 274.72
Proposed Coverage Area ( 59.19 % ) 271.02
Total Prop. Coverage Area ( 59.19 % ) 271.02
Balance coverage area ( 0.81 % ) 3.70
FAR CHECK
Perm. FAR Area ( 2.50 ) 1144.68
Total Perm. FAR area 1144.68
Residential FAR 261.51
Commercial FAR 538.16
Proposed FAR Area 811.43
Total Proposed FAR Area 811.43
Consumed FAR (Factor) 1.77
Balance FAR Area 333.25
BUA CHECK
Total Proposed BuiltUp Area 1075.54


[-] Site Visit Data Report
Details Values as per Site Visit Values as per Drawing
Lenght of Road Up to 50 meter -
Existing Road Width 14.68 14.68
Proposed Road Width as per Master Plan 0 -
Road Widening Width 0 -
Plot size (as per measurement) 457.87 457.87
[-] Extra Land Area Checks
Name Area Status
Reqd Prop
Extra Land - 0.00 OK
   



[-] Rules
Topic Rule
Plot Level
Plot Area No rule provided for Min. Plot size for proposed Use or Multistoried Building {Updated as per JBBL, Amendment VIII dated 16/03/2021}
Plot Width No rule provided for Min. Plot size for proposed Use or Multistoried Building {Updated as per JBBL, Amendment VIII dated 16/03/2021}
Plot Depth No rule provided for Min. Plot size for proposed Use or Multistoried Building {Updated as per JBBL, Amendment VIII dated 16/03/2021}
Access Width The minimum width of abutting road for any Building shall be with respect to Length of Road {As per Rule No. 34 Table No.6}
Plot Frontage No rule provided for Min. Plot size for proposed Use or Multistoried Building {Updated as per JBBL, Amendment VIII dated 16/03/2021}
FAR Area (1) In Old Area, for Non-Residential Building on abutting roadwidth 12.20 (40 ft.) to 18.30 mt., the Floor Area Ratio-FAR shall be 2.5 {As per Rule No.39, Table 15}
(2) For Chas Municipal Corporation, Max. 2.5 permissible FAR may be permitted for Commercial or Mercantile type Use {As per Annexure III}
Consumed FAR (1) In Old Area, for Non-Residential Building on abutting roadwidth 12.20 (40 ft.) to 18.30 mt., the Floor Area Ratio-FAR shall be 2.5 {As per Rule No.39, Table 15}
(2) For Chas Municipal Corporation, Max. 2.5 permissible FAR may be permitted for Commercial or Mercantile type Use {As per Annexure III}
Common Plot Area In case of multi-storied buildings/ Group Housing /Apartment building/ Industrial/ Assembly/ Educational/ Institutional buildings, it is desirable that at least 10% of the land shall be covered by plantation (tree cover) {As per Rule No.33}
Common Plot (1) In case of multi-storied buildings/ Group Housing /Apartment building/ Industrial/ Assembly/ Educational/ Institutional buildings, it is desirable that at least 10% of the land shall be covered by plantation (tree cover) {As per Rule No.33}
(2) ;
Tree Number 4-8 Trees shall be required for the Plot area above 250.0 and upto 1000.0 sq.mt. (As per Rule No. 20.1.6)
DriveWay Rule The minimum width of the drive way meant exclusively for 2 wheelers should be 3.0 mt {As per Rule No. 41.2}
Margin Rule For Non-highrise Residential Building 10-13.3 mt. Ht. having Plot Depth 45 or above mt. and Plot width upto 10 mt., Margin required in Front shall be 5.0 mt., Rear 5.0 mt. and 0.9 mt. shall be provided on both side. {As per Rule No. 36 (Table 8 & 9)}
Building Level
Building Height For old area, on Road width 12.20-18.30 mt., Permissible height shall in no case exceed(1.5 times the width oftheroadonwhichtheplot abuts) + Road widening + the front setback or 30.0 mt. {As per Rule No. 39.1 Table 15}
Floor Height (1) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
(2) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
(3) The plinth or any part of a building shall be so located with respect to the surrounding ground level that adequate drainage of the site is assured. The height of the plinth (except in case of stilted parking) shall be not less than 0.45 mt. from the surrounding ground level {As per Rule No. 42.10}
Parapet Height Parapet of suitable height may be constructed to hide installation like water tank and for other such purpose {As per Rule No. 42.5 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
Floor Number For old area location,on Road width 12.20-18.30 mt., Maximum Height 30 meter shall be allowed. {As per Rule No. 39.1 Table 15}
Lift Count (1) The lift shall have a minimum width 1.7 mt. and minimum depth 1.9 mt.{As per clause no 4 and page no. 14 NBC }
(2) For Residential Building height upto 15.0 mt or upto G+4 floors, No Lift is reqd. {As per Amended 06-06-2019 Rule No. 49.1.1}
Lift (1) The area of lift well shall not be counted for F.A.R calculation)
(2) The lift shall have a minimum width 1.7 mt. and minimum depth 1.9 mt.{As per clause no 4 and page no. 14 NBC }
(3) The area of lift well at one floor only (not the sum of total area of lift well at every floor) shall be counted for F.A.R calculation)
(4) The lift shall have a minimum width 1.7 mt. and minimum depth 1.9 mt.{As per clause no 4 and page no. 14 NBC }
(5) -
StairCase (1) Width of Winding staircase shall be mini. 0.90 mt.,Maximum rise 0.20 mt. & Minimum tread 0.25 mt. & Cabin Height 2.1 mt. {As per Rule No. 83.18}
(2) ; No Rule Defined
(3) No Rule Defined
(4) ; No Rule Defined
Ramp No Need to Check Natural Slope width, Depth or height. ;
Ramp No. For parking spaces in basements and upper storey of parking floors, if car parking is less then 40 one ramp of minimum of 3.30m width if it is straight and 4.50m width if it is curved shall be provided
Plot / Building Level
Accessory Use (1) Common toilet of maximum size of 5 sq.mt shall be taken Free from FAR
(2) No need to check distance from Building Toilet
(3) -
(4) No need to check distance from Building SUMP TANK
(5) The dimension of recharging pits/trenches shall be at least 6 cubic meters for every 100 Sq. m. of roof area
(6) No need to check distance from Building RAIN WATER HARVESTING
(7) No need to check distance from Building ENT.GATE
(8) -
(9) No need to check distance from Building SOLAR HEATING SYSTEM
Accessory Use Number (1) Provision of Rain Water Harvesting shall be mandatory for any use {Updated as per JBBL, Amendment VIII dated 16/03/2021} Rain Water Harvesting
(2) In case of buildings with a height of 15.0 meters and above or ground coverage more than 500 sqm., the main entrance to the premise shall not be less than 5 (five) meters i n width in order to allow easy access to fire engine Entrance Gate
Building Level (Rooms)