No Image Found   

Detail Scrutiny Report

Mango Municipal Corporation

Version Number: 1.0.62  
Version Date: 16/10/2020 
Report Generated On: 28-02-2022 
 
[-] Collapse All


General Details
RegionJHARKHAND URBAN LOCAL BODIES
DistrictEAST SINGHBHUM
AuthorityMANGO MUNICIPAL CORPORATION
Inward_NoMNAC/BP/0061/W08/2021
Application TypeGeneral Proposal
Project TypeBuilding Permission
Nature of DevelopmentNew
Location of Development AreaOld Area
City Area/TPScheme NoNA
VillageMango
Taluka16
Architect Details
Architect NameSURAJIT SENGUPTA
License No.MNAC/ARC/0002/2021
Architect AddressMerujeen Housing Complex,Blk-A5,Flat 131,Ramchandrapur road
Architect EmailIDsurajit@salientdesignstudio.com
Architect Mobile No9007097776
Plot Details
Plot Use Commercial
Plot SubUse Shop cum residence
PlotNearbyReligiousStructure NA
Plot/SubPlot No136
North -
South -
East -
West -
Owner's Details
NameAAKASH INDIA PROJECTS AND BUILDERS PVT. LTD.
AddressPAYAL CINEMA COMPLEX, MANGO, JAMSHEDPUR
Email IDvishal@aakashindia.in
Mobile No9334800628
[-] Plot Details (Table 2)

[-] Area From Document (Table 2a)
No. Form Area
1 Deed(Sale Deed, Gift Deed and Lease Deed) or Agreement 4977.00
2 Plot area as per Document by Applicant 4977.00
3 Physical area measured at site 4977.00
4 Area as per Site Visit (Site Visit Report) 4977.00
5Area as per Drawing 4977.03

Area of Plot Considered : 4977.00

Plot area provided in drawing shall not be more than Plot area as per Document.
[-] Table 2b
Proposal Detail :
UnitMeters
Development Detail :
PlotPLOT
Plot OccupancyCommercial
Plot SubUse Shop cum residence
Building StructureMultistoried
Building TypeSingle Detached House
Gross Plot Area 4977.00
Net Plot Area (Gross Plot Area - Deduction from Gross Plot area) 4977.00
Balance Plot Area (Net Plot Area - Recreational/Amenity space) 4977.00

[-] Table 2c
COVERAGE CHECK
Permissible Coverage area ( 50.00 % ) 2488.50
Proposed Coverage Area ( 37.46 % ) 1864.24
Total Prop. Coverage Area ( 37.46 % ) 1864.24
Balance coverage area ( 12.54 % ) 624.26
FAR CHECK
Perm. FAR Area ( 3.00 ) 14931.00
Total Perm. FAR area 14931.00
Residential FAR 8684.04
Commercial FAR 5171.46
Special FAR 312.96
Proposed FAR Area 14269.22
Total Proposed FAR Area 14269.22
Consumed FAR (Factor) 2.87
Balance FAR Area 661.78
BUA CHECK
Total Proposed BuiltUp Area 16749.94


[-] Site Visit Data Report
Details Values as per Site Visit Values as per Drawing
Lenght of Road Up to 50 meter -
Existing Road Width 21 21.00
Proposed Road Width as per Master Plan 21 -
Road Widening Width 0 -
Plot size (as per measurement) 4977 4977.03
[-] Extra Land Area Checks
Name Area Status
Reqd Prop
Extra Land - 0.00 OK


[-] Plot Level Checking (Table 3)
   
[-] Tree Details (Table 3g)
Name Nos Of Trees Status
Reqd Prop
Tree 8 8 OK
   
   
   
   
   
     
   


[-] Building Details (Table 4)
   
[-] Building USE/SUBUSE Details Building USE/SUBUSE Details
Building Name Building Use Building SubUse Building Structure
A (AAKASH SKYLINE) Commercial Shop cum residence Multistoried
   
   
   
[-] Height Details (4a)



[-] Total Height (Table 4a-1)
Building Height Height (From GL) Height (From Street LVL) Status
Perm Prop
A (AAKASH SKYLINE) 52.00 46.90 46.90 46.90 OK


   
   
[-] Floor Height Check (Table 4a-2)
Building Name Floor Name Height Clear Height Beam Clear Height Status
Reqd Perm Prop Reqd Perm Prop Reqd Perm Prop
A (AAKASH SKYLINE) Thirteenth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Twelfth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Eleventh Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Tenth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Ninth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Eighth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Seventh Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Sixth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Fifth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Fourth Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Third Floor 2.75 - 2.95 2.75 - 2.85 2.40 - 2.45 OK
Second Floor 2.75 - 3.05 2.75 - 2.95 2.40 - 2.45 OK
First Floor 2.75 - 4.80 2.75 - 4.60 2.40 - 3.90 OK
Upper Ground Floor 2.75 - 3.90 2.75 - 3.80 2.40 - 3.40 OK
Lower Ground Floor 2.75 - 3.60 2.75 - 3.50 2.40 - 3.00 OK
Basement Floor - - 4.00 - - 3.80 - - 3.30 OK


[-] Parapet Height Check (Table 4a-2.1)
Building Name Floor Name Height Status
Reqd Perm Prop
A (AAKASH SKYLINE) Terrace Floor - - 1.50 OK
   
   
[-] Basement Floor Check (Table 4a-3)
Building Name Floor Name Height Below GL Area Ventilation Area (Sq.mt.) Status
Perm Prop Perm Prop Reqd Prop
A (AAKASH SKYLINE) Basement Floor - 4.00 - 2229.43 - 0.00 OK


[-] Basement Floor Area Check
Building Name Area Status
Perm Prop
A (AAKASH SKYLINE) - 2229.43
Total - 2229.43 OK

1 [-] Basement Margin Check
Building / Wing Road Name Front Side Rear Side Side1 Side2 Status
Reqd. Prop. Reqd. Prop. Reqd. Prop. Reqd. Prop.
  A-1 (AAKASH SKYLINE)   21.00 M WIDE ROAD 3.00 4.83 3.00 10.02 3.00 11.64 3.00 3.80 OK

    >
   
   
[-] Floor Number Check (Table 4a-4)
Building Name No. of Floors No. of Tenements Status
Perm Prop Perm Prop
A (AAKASH SKYLINE) - 15 - 96 OK




Not Required to Check Basement Floor Number Rule.
 
   
    [-] Coverage Check (Table 4b)
Permissible Proposed Status
2488.50 1864.24 OK
50% 37.46%

[-] Individual Coverage Check
Coverage Area Perm. Prop.
  A-1 (AAKASH SKYLINE) - 1864.24
  Total Prop. Coverage Area - 1864.24
  Total Coverage Area 2488.50 1864.24

[-] FAR & Tenement Details (Table 4c-1)
Building No. of Same Bldg Gross Built Up Area (Sq.mt.) Deductions From Gross BUA(Area in Sq.mt.) Total Built Up Area (Sq.mt.) Deductions (Area in Sq.mt.) Proposed FAR Area (Sq.mt.) Add Area In FAR (Sq.mt.) Total FAR Area (Sq.mt.) Total Consumed Additional FAR Area (Sq.mt.) Tnmt (No.)
Cutout StairCase Balcony Parking Resi. Commercial Public Utility Stair
A (AAKASH SKYLINE) 1 17131.34 381.40 16749.94 233.92 120.74 2126.05 8684.05 5171.46 312.96 69.15 14269.22 14269.22 96
Grand Total : 1 17131.34 381.40 16749.94 233.92 120.74 2126.05 8684.05 5171.46 312.96 69.15 14269.22 14269.22 96


[-] Buildingwise Floor FAR Details
Floor Name Building Name Total
A (AAKASH SKYLINE)
Proposed Built Up Area (Sq.mt.) Proposed FAR Area (Sq.mt.) Total Proposed Built Up Area (Sq.mt.) Total FAR Area (Sq.mt.)
Basement Floor 2229.43 88.75 2229.43 88.75
Lower Ground Floor 1619.24 1604.62 1619.24 1604.62
Upper Ground Floor 1878.86 1864.24 1878.86 1864.24
First Floor 1717.22 1702.60 1717.22 1702.60
Second Floor 865.68 844.17 865.68 844.17
Third Floor 768.26 743.29 768.26 743.29
Fourth Floor 768.26 743.29 768.26 743.29
Fifth Floor 768.26 743.29 768.26 743.29
Sixth Floor 783.26 758.29 783.26 758.29
Seventh Floor 768.26 743.29 768.26 743.29
Eighth Floor 768.26 743.29 768.26 743.29
Ninth Floor 768.26 743.29 768.26 743.29
Tenth Floor 768.26 743.29 768.26 743.29
Eleventh Floor 783.26 758.29 783.26 758.29
Twelfth Floor 783.26 758.29 783.26 758.29
Thirteenth Floor 699.91 674.94 699.91 674.94
Terrace Floor 12.00 12.00 12.00 12.00
Total : 16749.94 14269.22 16749.94 14269.22


[-] UnitBUA Table for Building :A (AAKASH SKYLINE)
UnitBUA CALCULATION
FLOOR Name UnitBUA Type UnitBUA Area Carpet Area No. of Rooms No. of Tenement
LOWER GROUND FLOOR PLAN MAIN ANCHOR SHOP 1335.90 1307.55 3 2
OFFICE G OFFICE 47.97 47.33 2
UPPER GROUND FLOOR PLAN 1 SHOP 171.28 162.39 1 12
10 SHOP 118.62 112.16 1
11 SHOP 31.75 30.55 2
2 SHOP 103.31 98.62 3
3 SHOP 18.11 17.54 1
4 SHOP 122.19 115.39 3
5 SHOP 170.19 163.72 9
6 SHOP 68.13 67.17 2
7 SHOP 203.27 191.43 6
8 SHOP 76.54 73.21 1
9 SHOP 16.15 15.75 1
CAFE SHOP 56.12 54.70 1
FIRST FLOOR PLAN 21 SHOP 133.10 125.64 1 10
22 SHOP 103.31 98.62 3
23 SHOP 18.11 17.56 1
24 SHOP 122.21 113.68 5
25 SHOP 170.19 163.94 9
26 SHOP 78.07 76.19 3
27 SHOP 203.27 190.63 7
28 SHOP 73.21 71.43 1
29 SHOP 16.15 15.78 1
30 SHOP 171.11 164.14 1
TOILET OTHER 0.00 0.00 1
SECOND FLOOR PLAN COMMUNITY HALL Public Utility Area 215.58 200.33 4 6
GYM Public Utility Area 51.04 47.33 1
UNIT 1 FLAT 104.10 92.18 9
UNIT 2 FLAT 97.72 86.35 8
UNIT 3 FLAT 116.90 102.43 10
UNIT 4 FLAT 105.28 92.19 9
TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN UNIT 11 FLAT 103.44 91.57 9 42
UNIT 12 FLAT 97.72 85.80 8
UNIT 13 FLAT 116.90 102.23 10
UNIT 14 FLAT 103.44 91.57 9
UNIT 15 FLAT 97.50 85.61 8
UNIT 16 FLAT 123.98 109.40 11
TYPICAL - 6& 11 FLOOR PLAN UNIT 21 FLAT 103.44 91.57 9 12
UNIT 22 FLAT 97.72 85.80 8
UNIT 23 FLAT 116.90 102.23 10
UNIT 24 FLAT 103.44 91.57 9
UNIT 25 FLAT 97.50 85.61 8
UNIT 26 FLAT 123.98 109.40 11
TWELFTH FLOOR PLAN UNIT 31 FLAT 103.44 92.09 7 6
UNIT 32 FLAT 97.72 86.17 7
UNIT 33 FLAT 116.90 102.47 9
UNIT 34 FLAT 103.44 92.09 7
UNIT 35 FLAT 97.50 86.09 7
UNIT 36 FLAT 123.98 109.25 10
THIRTEENTH FLOOR PLAN UNIT 41 FLAT 91.79 80.43 7 6
UNIT 42 FLAT 86.38 75.21 6
UNIT 43 FLAT 105.56 90.49 8
UNIT 44 FLAT 92.10 80.75 7
UNIT 45 FLAT 86.16 75.07 6
UNIT 46 FLAT 112.64 97.67 9
Total: - - 11323.21 10279.26 695 96


[-] Building :A (AAKASH SKYLINE)
Floor Name Gross Builtup Area Deductions From Gross BUA(Area in Sq.mt.) Total Built Up Area (Sq.mt.) Deductions (Area in Sq.mt.) Proposed FAR Area (Sq.mt.) Add Area In FAR (Sq.mt.) Total FAR Area (Sq.mt.) Total Consumed Additional FAR Area (Sq.mt.) Tnmt (No.)
Cutout StairCase Balcony Parking Resi. Commercial Public Utility Stair
Basement Floor 2229.43 0.00 2229.43 14.62 0.00 2126.05 0.00 0.00 0.00 69.15 88.75 88.75 00
Lower Ground Floor 1619.24 0.00 1619.24 14.62 0.00 0.00 0.00 1604.62 0.00 0.00 1604.62 1604.62 02
Upper Ground Floor 1878.86 0.00 1878.86 14.62 0.00 0.00 0.00 1864.24 0.00 0.00 1864.24 1864.24 12
First Floor 1851.23 134.01 1717.22 14.62 0.00 0.00 0.00 1702.60 0.00 0.00 1702.60 1702.60 10
Second Floor 880.60 14.92 865.68 14.62 6.89 0.00 531.21 0.00 312.96 0.00 844.17 844.17 06
Third Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Fourth Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Fifth Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Sixth Floor 798.18 14.92 783.26 14.62 10.35 0.00 758.29 0.00 0.00 0.00 758.29 758.29 06
Seventh Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Eighth Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Ninth Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Tenth Floor 783.18 14.92 768.26 14.62 10.35 0.00 743.29 0.00 0.00 0.00 743.29 743.29 06
Eleventh Floor 798.18 14.92 783.26 14.62 10.35 0.00 758.29 0.00 0.00 0.00 758.29 758.29 06
Twelfth Floor 798.18 14.92 783.26 14.62 10.35 0.00 758.29 0.00 0.00 0.00 758.29 758.29 06
Thirteenth Floor 783.18 83.27 699.91 14.62 10.35 0.00 674.94 0.00 0.00 0.00 674.94 674.94 06
Terrace Floor 12.00 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.00 12.00 00
Total : 17131.34 381.40 16749.94 233.92 120.74 2126.05 8684.05 5171.46 312.96 69.15 14269.22 14269.22 96
Total Number of Same Buildings : 1
Total : 17131.34 381.40 16749.94 233.92 120.74 2126.05 8684.05 5171.46 312.96 69.15 14269.22 14269.22 96
[-] Table 4c-2

  FAR Area
Building FAR Area:14330.33
Existing FAR Area :0.00
Perm.
14931.00
Prop.
14330.33
Status
OK




[-] Margin Checks (Table 5)
   
[-] Plot Margin (Table 5a)
Building / Wing Road Name Front Side Rear Side Side1 Side2 Status
Reqd. Prop. Reqd. Prop. Reqd. Prop. Reqd. Prop.
A-1 (AAKASH SKYLINE) 21.00 M WIDE ROAD 13.00 21.41 10.00 10.29 10.00 12.31 10.00 10.00 OK






[-] Inner Building Details (Table 6)
   
   
[-] Balcony Details (Table 6c)

[-] For Building:A (AAKASH SKYLINE)
Floor Name Balcony Name Width Status
Perm Prop
SECOND FLOOR PLAN BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
TYPICAL - 6& 11 FLOOR PLAN BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
TWELFTH FLOOR PLAN BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
THIRTEENTH FLOOR PLAN BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK
BALCONY 1.20 1.20 OK



For PWork At Layout : 

No Balcony Found.

   
   
   
[-] Passage Details

[-] For Building :A (AAKASH SKYLINE)
Floor Name Passage Name Area Width Length Status
Prop Reqd Prop Perm Prop
UPPER GROUND FLOOR PLAN 2.75 mt. Wide Passage 116.19 1.00 2.72 - 42.25 OK
3.00 mt. Wide Passage 97.89 1.00 2.97 - 32.62 OK
FIRST FLOOR PLAN 3.00 mt. Wide Passage 126.75 1.00 2.97 - 42.25 OK
3.00 mt. Wide Passage 61.50 1.00 2.97 - 20.50 OK
3.00 mt. Wide Passage 108.47 1.00 2.97 - 36.15 OK
1.75 mt. Wide Passage 14.83 1.00 1.60 - 9.13 OK
4.88 mt. Wide Passage 40.83 1.00 4.85 - 8.38 OK

   
   
   
[-] Lift Details (Table 6d)
Building Name Height Status
Prop
A (AAKASH SKYLINE) 46.90 OK

[-] Lift Check Table

[-] For Building :A (AAKASH SKYLINE)
Floor Name Lift Name Width Depth Status
Reqd Prop Reqd Prop
BASEMENT FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
LOWER GROUND FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
UPPER GROUND FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
FIRST FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
Lift 1.70 1.90 1.90 2.00 OK
SECOND FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
TYPICAL - 6& 11 FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
TWELFTH FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
THIRTEENTH FLOOR PLAN Lift 1.70 2.00 1.90 2.50 OK
Lift 1.70 1.75 1.90 2.00 OK
Lift 1.70 1.75 1.90 2.00 OK
TERRACE FLOOR PLAN Lift Machine Room 1.70 2.00 1.90 2.50 OK
Lift Machine Room 1.70 1.75 1.90 2.00 OK
Lift Machine Room 1.70 1.75 1.90 2.00 OK

   


[-] Parking Details (Table 7)
   
[-] Required Parking(Table 7a)
Building Name Type SubUse Area (Sq.mt.) Units Car Visitors Car TwoWheeler
Reqd. Prop. Reqd./Unit Reqd. Prop. Reqd./Unit Reqd. Prop. Reqd./Unit Reqd. Prop.
A (AAKASH SKYLINE) Commercial Shop > 0 100 4245.92 1 29 - - - - - - -
> 0 100 4245.92 - - - - - - 1 89 -
Residential Residential Bldg/Apartment > 0 1 70.00 1.00 70 - - - - - - -
> 0 1 70.00 - - - - - - 1 70 -
> 0 1 70.00 - - - 1 7 - - - -
Public Utility Public Utility Bldg > 0 100 312.96 1 3 - - - - - - -
> 0 100 312.96 - - - - - - 1 7 -
Total : - - - - 102 104 - 7 7 - 166 170

[-] Parking Check (Table 7b)
Vehicle Type Reqd. Prop. Status
No. Area No. Area
Car - - 104 1300.00 OK
Total Car 102 1275.00 104 1300.00 OK
Visitor's Car Parking - - 7 87.50 OK
Total Visitor Parking 7 87.50 7 87.50 OK
TwoWheeler - - 170 340.00 OK
Total TwoWheeler 166 332.00 170 340.00 OK
Other Parking - - - 1221.55 OK
Total 1694.50 3289.05 OK

Individual Parking Checks (Table 7c)
Dimensions and Area for all Vehicle(s) are as per the Rules

[-] Driveway Parking Checks (Table 7d)
Building/Plot Name Floor Name Driveway Name Width Status
Reqd Perm Prop
PLOT - DRIVEWAY6 4.50 - 4.60 OK
DRIVEWAY5 3.00 - 5.00 OK
A (AAKASH SKYLINE) BASEMENT FLOOR PLAN DRIVEWAY1 4.50 - 4.93 OK
DRIVEWAY2 4.50 - 5.00 OK
DRIVEWAY4 4.50 - 5.01 OK
DRIVEWAY3 4.50 - 4.50 OK
DRIVEWAY7 4.50 - 4.50 OK

   


[-] Exemption Details (Table 8)
   


Not Required to Check StairCase Number Rule.


[-] Staircase Checks (Table 8a-1)


[-] For Building :A (AAKASH SKYLINE)
Floor Name StairCase Name Flight Width Floor Landing Width Tread Width Riser Height Riser No. On Flight Cabin Ht. Status
Reqd Prop Perm Prop Reqd Prop Perm Prop Perm Prop Reqd Perm Prop
BASEMENT FLOOR PLAN Fire Escape Staircase - 1.250 - 0.000 - 0.250 - 0.000 - 0 - - 0.000 OK
Staircase -3FL - 1.250 - 0.000 - 0.250 - 0.000 - 0 - - 0.000 OK
Staircase -4FL - 1.800 - 0.000 - 0.300 - 0.000 - 0 - - 0.000 OK
Staircase -4FL - 1.950 - 0.000 - 0.300 - 0.000 - 0 - - 0.000 OK
LOWER GROUND FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.164 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.129 - 8 - - 0.000 OK
Escalator - 1.274 - 0.220 - 0.106 - 17 - - 0.000 OK
Staircase -4FL 0.900 1.800 0.250 0.300 0.200 0.069 - 10 - - 0.000 OK
Staircase -4FL 0.900 1.950 0.250 0.300 0.200 0.069 - 12 - - 0.000 OK
UPPER GROUND FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.177 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.139 - 8 - - 0.000 OK
Escalator - 1.274 - 0.220 - 0.115 - 17 - - 0.000 OK
Staircase -4FL 0.900 1.800 0.250 0.300 0.200 0.075 - 10 - - 0.000 OK
Staircase -4FL 0.900 1.950 0.250 0.300 0.200 0.075 - 12 - - 0.000 OK
FIRST FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.200 16 10 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.171 - 8 - - 0.000 OK
Staircase -4FL 0.900 1.800 0.250 0.300 0.200 0.092 - 10 - - 0.000 OK
Staircase -4FL 0.900 1.950 0.250 0.300 0.200 0.092 - 12 - - 0.000 OK
Escalator - 1.274 - 0.220 - 0.141 - 17 - - 0.000 OK
SECOND FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.139 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.109 - 8 - - 0.000 OK
TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.134 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.105 - 8 - - 0.000 OK
TYPICAL - 6& 11 FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.134 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.105 - 8 - - 0.000 OK
TWELFTH FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.134 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.105 - 8 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 11 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 7 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
THIRTEENTH FLOOR PLAN Fire Escape Staircase 0.900 1.250 0.250 0.250 0.200 0.134 16 9 - - 0.000 OK
Staircase -3FL 0.900 1.250 0.250 0.250 0.200 0.105 - 8 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 11 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 7 - - 0.000 OK
Internal Staircase - 1.000 - 0.250 - 0.148 14 10 - - 0.000 OK
TERRACE FLOOR PLAN Fire Escape Staircase - 1.250 - 0.000 - 0.250 - 0.000 - 0 - - 2.534 OK
Staircase -3FL - 1.250 - 0.000 - 0.250 - 0.000 - 0 - - 2.534 OK

   
   
   

[-] Ramp Checks (Table 8b-a)
Ramp Name Depth Status
Reqd Prop
25.00 mt. long 1.80 mt. High 3.60 mt. Wide Car Ramp - 1.80 OK
17.85 mt. long 1.50 mt. High 3.60 mt. Wide Car Ramp - 1.50 OK
15.20 mt. long 1.50 mt. High 5.00 mt. Wide Car Ramp - 1.50 OK


[-] Ramp Checks (Table 8b)
Building Name Floor Name No. Status
Reqd Prop
A (AAKASH SKYLINE) BASEMENT FLOOR PLAN 2 3 OK

   
   
[-] Arch Projection Checks (Table 8c - a)

[-] For Building :A (AAKASH SKYLINE)
Floor Name Arch Proj Name Width Depth Area Status
Perm Prop Perm Prop Perm Prop
SECOND FLOOR PLAN WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.63 - 0.98 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.50 - 2.63 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.63 - 0.98 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
TYPICAL - 6& 11 FLOOR PLAN WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.50 - 2.63 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.63 - 0.98 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
TWELFTH FLOOR PLAN WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.50 - 2.63 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.63 - 0.98 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
THIRTEENTH FLOOR PLAN WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 13.00 - 9.75 OK
WeatherShed 0.75 0.75 - 2.98 - 2.23 OK
WeatherShed 0.75 0.75 - 3.50 - 2.63 OK
WeatherShed 0.75 0.75 - 3.00 - 2.25 OK
WeatherShed 0.75 0.75 - 3.95 - 2.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.63 - 0.98 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
C.B. 0.60 0.60 - 1.60 - 0.96 OK
   
   
   
[-] Accessory Use Check (Table 8d)
Accessory Use Name Area Width Depth Height Status
Reqd Perm Prop Reqd Perm Prop Reqd Perm Prop Reqd Perm Prop
FIRE Refuse Chute - - 15.00 - - 4.00 - - 4.70 - - 0.00 OK
FIRE Refuse Chute - - 15.00 - - 4.00 - - 4.70 - - 0.00 OK
Toilet - 5.00 3.00 - - 1.50 - - 2.00 - - 0.00 OK
RAIN WATER HARVESTING 3.00 DIA & 3.6 M DEPTH - - 6.88 - - 2.96 - - 2.96 - - 0.00 OK
METER ROOM - - 48.73 - - 4.73 - - 10.31 - - 0.00 OK
ENT.GATE - - 2.50 - - 0.50 - - 5.00 - - 0.00 OK


   
   


[-] Floor Details (Table 9)
   

[-] Building:A (AAKASH SKYLINE)


[-] Floor:BASEMENT FLOOR PLAN



No Room Found.


[-] Floor:LOWER GROUND FLOOR PLAN



Not Required to Check Dimensions and Area of all the Rooms on this Floor Rule.

[-] Floor:UPPER GROUND FLOOR PLAN



Not Required to Check Dimensions and Area of all the Rooms on this Floor Rule.

[-] Floor:FIRST FLOOR PLAN



Not Required to Check Dimensions and Area of all the Rooms on this Floor Rule.

[-] Floor:SECOND FLOOR PLAN



All Dimensions and Area of all the Rooms on this Floor are as per the Rules.

[-] Floor:TYPICAL - 3, 4, 5, 7, 8, 9& 10 FLOOR PLAN



All Dimensions and Area of all the Rooms on this Floor are as per the Rules.

[-] Floor:TYPICAL - 6& 11 FLOOR PLAN



All Dimensions and Area of all the Rooms on this Floor are as per the Rules.

[-] Floor:TWELFTH FLOOR PLAN



All Dimensions and Area of all the Rooms on this Floor are as per the Rules.

[-] Floor:THIRTEENTH FLOOR PLAN



All Dimensions and Area of all the Rooms on this Floor are as per the Rules.


   


[-] Summary (Table 10)
   
Name Perm./Reqd. Proposed Status
  Plot Area - 4977.00 OK
  Plot Width - 62.29 OK
  Plot Depth - 79.90 OK
  Access Width - 21.00 OK
  Plot Frontage - 64.57 OK
  Coverage Area 2488.50 1864.24 OK
  FAR Area
Bldg. FAR Area : 14330.33
Sanctioned FAR Area :0.00
14931.00 14330.33 OK




</

[-] Rules
Topic Rule
Plot Level
Plot Area The depth of plot shall be max. 10 mt. for Shop-cum-Residence Building {As per Chapter VII, Rule No. 66.8 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
Plot Width The depth of plot shall be max. 10 mt. for Shop-cum-Residence Building {As per Chapter VII, Rule No. 66.8 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
Plot Depth The depth of plot shall be max. 10 mt. for Shop-cum-Residence Building {As per Chapter VII, Rule No. 66.8 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
Plot Frontage The depth of plot shall be max. 10 mt. for Shop-cum-Residence Building {As per Chapter VII, Rule No. 66.8 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
FAR Area (1) 0.0
(2) 0.0
Consumed FAR (1) 0.0
(2) 0.0
Tree Number Mini. 8 Trees shall be required for the Plot area above 1000.0 sq.mt. (As per Rule No. 20.1.6)
DriveWay Rule (1) For Plor area above 2000 sq.mt., The minimum width or driveways should not be less than 4.50 mt. {As per Rule No. 41.2 and modified as per Notification from Govt. of Jharkhand 3141 dated 15/05/2017}
(2) The minimum width of the drive way meant exclusively for 2 wheelers should be 3.0 mt {As per Rule No. 41.2}
Building Level
Building Height For shop cum residence, Permissible height shall in no case exceed(1.5 times the width oftheroadonwhichtheplot abuts) + Road widening + the front setback or 12.0 mt. {As per Chapter VII}
Floor Height (1) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
(2) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
(3) No rule found for Mini. reqd Floor height
Below GL Floor Height ,
Balcony Projected balcony may be allowed with a width of 1.2 mt. where the setback is more than 4.5 mt. and 4.5 mt. respectively clear driveway is available for the Fire tender movement {As per Rule No. 46.4 and modified as per Notification from Govt. of Jharkhand 3141 dated 15/05/2017 and Updated as per JBBL, Amendment VIII dated 16/03/2021}
Passage No exit doorway shall be less than 1.00 m. in width. {As per Rule No.43.4.2} ;
Lift The lift shall have a minimum width 1.7 mt. and minimum depth 1.9 mt.{As per clause no 4 and page no. 14 NBC }
StairCase (1) Width of the Fire Stair case shall be mini. 0.90 mt.,Maximum rise 0.20 mt. & Minimum tread 0.25 mt. {As per Rule No. 43.5.3.6}
(2) ; Number of riser shall not exceed 16 per flight of stairs. {As per Rule No. 43.5.3.6}
(3) Width of Winding staircase shall be mini. 0.90 mt.,Maximum rise 0.20 mt. & Minimum tread 0.25 mt. & Cabin Height 2.1 mt. {As per Rule No. 83.18}
(4) ; No Rule Defined
(5) No Rule Defined
(6) ; No Rule Defined
(7) No Rule Defined
(8) ; Number of riser shall not exceed 14 per flight of stairs. {As per Rule No. 43.5.2.6}
Ramp No. For parking spaces in basements and upper storey of parking floors, if car parking is more then 40 two ramp of minimum of 3.30m width if it is straight and 3.60m width if it is curved and 5.4m width if one ramp is required shall be provided
Arch Projection (1) Chhajja,Cornice or Weather shed of upto 0.75m width shall be permitted. {As per Rule No. 46.1}
(2) Cupboard up to 0.60 mt. in width shall be permitted. {As per Rule 6.26.1 and modified as per Notification from Govt. of Jharkhand 3141 dated 15/05/2017}
Plot / Building Level
Accessory Use (1) - FIRE Refuse Chute
(2) Common toilet of maximum size of 5 sq.mt shall be taken Free from FAR Toilet
(3) The dimension of recharging pits/trenches shall be at least 6 cubic meters for every 100 Sq. m. of roof area RAIN WATER HARVESTING 3.00 DIA & 3.6 M DEPTH
(4) Electric cabin or substation of maximum size of 4 sq.m. with minimum width or diameter of 2 m METER ROOM
(5) ENT.GATE
Building Level (Rooms)