No Image Found   

Check List Report

Mineral Area Development Authority

Version Number: 1.0.48  
Version Date: 22/06/2020 
Report Generated On: 24-09-2020 
 

[-] Collapse All


General Details
RegionJHARKHAND URBAN LOCAL BODIES
DistrictDHANBAD
AuthorityMINERAL AREA DEVELOMENT AUTHORITY
Inward_NoMADA/BP/0027/2019
Application TypeGeneral Proposal
Project TypeBuilding Permission
Nature of DevelopmentNew
Location of Development AreaOld Area
City Area/TPScheme NoNA
VillageKurmidih
Taluka15
Architect Details
Architect NameASHOK KUMAR
License No.MADA/ENG/0007/2019
Architect Address3A, 4th floor, Bhupendra Shanti Apartment, J.P Nagar DHANBAD
Architect EmailIDhdassociate02@gmail.com
Architect Mobile No7903779603
Plot Details
Plot Use Residential
Plot SubUse Bungalow/ Dwelling / Non Apartment
PlotNearbyReligiousStructure NA
Plot/SubPlot NoOLD - 1416 NEW - 2464
NorthRoad Width - 3.66
SouthPlot No. - PART OF SAME PLOT
EastPlot No. - MD. AFTAB ALAM
WestRoad Width - 3.66 VILLAGE ROAD
Owner's Details
NameMD. HASAN NEZAMI
AddressSHAMSHER NAGAR, P.S. - JHARIA, DIST- DHANBAD
Email IDtauquirnishat@gmail.com
Mobile No9835390325
[-] Plot Details (Table 2)

[-] Area From Document (Table 2a)
No. Form Area
1 Deed(Sale Deed, Gift Deed and Lease Deed) or Agreement 202.32
2 Plot area as per Document by Applicant 202.32
3 Physical area measured at site 194.64
4 Area as per Site Visit (Site Visit Report) 194.64
5Area as per Drawing 194.64

Area of Plot Considered : 194.64

[-] Table 2b
Proposal Detail :
UnitMeters
Development Detail :
PlotRESIDENTIAL
Plot OccupancyResidential
Plot SubUse Bungalow/ Dwelling / Non Apartment
Building StructureNon-Highrise
Building TypeSingle Detached House
Gross Plot Area 194.64
Net Plot Area (Gross Plot Area - Deduction from Gross Plot area) 194.64
Balance Plot Area (Net Plot Area - Recreational/Amenity space) 184.72
Deductions for Balance Plot Area (from Gross Plot Area)
- Common Plot 9.92
9.92
Balance Plot Area 184.72

[-] Table 2c
COVERAGE CHECK
Permissible Coverage area ( 70.00 % ) 136.25
Proposed Coverage Area ( 56.54 % ) 110.05
Total Prop. Coverage Area ( 56.54 % ) 110.05
Balance coverage area ( 13.46 % ) 26.20
FAR CHECK
Perm. FAR Area ( 1.50 ) 291.96
Total Perm. FAR area 291.96
Residential FAR 227.92
Proposed FAR Area 227.92
Total Proposed FAR Area 227.92
Consumed FAR (Factor) 1.17
Balance FAR Area 64.04
BUA CHECK
Total Proposed BuiltUp Area 235.74


[-] Site Visit Data Report
Details Values as per Site Visit Values as per Drawing
Lenght of Road Up to 50 meter -
Existing Road Width 4.57 4.57
Proposed Road Width as per Master Plan 3.6 -
Road Widening Width 0 -
Plot size (as per measurement) 194.64 194.64
[-] Extra Land Area Checks
Name Area Status
Reqd Prop
Extra Land - 0.00 OK

     Extra Land Area Details
Name Description Unit Reqd Perm Proposed Status
Extra Land Area Details Extra Land Area - - 0.00 OK

     Plot Related Details
Name Description Unit Reqd Perm Proposed Status
PLOT Plot Area Sq.Mt. - - 194.64 OK
Plot Width Mt. - - 13.97 OK
Plot Depth Mt. - - 13.94 OK
Access Width Mt. - - 4.57 OK
Plot Frontage Mt. - - 13.72 OK
Coverage Area Sq.Mt. - 136.25 110.05 OK
FAR Area Sq.Mt. - 291.96 227.92 OK
Consumed FAR Sq.Mt. - 1.50 1.17 OK
Common Plot Checks Common Plot - Total Area Sq.Mt. 9.73 9.92 OK
Common Plot Normal Open Space - Minimum Area Sq.Mt. - 9.92 OK
Normal Open Space - Access Mt. - OK
Tree Tree - Nos Of Trees No. 2 3 OK
A-1 (NEZAMI) Front Margin... 4.57 MT. WD. ROAD Mt. 2.00 - 2.05 OK
Rear Margin Mt. 1.50 - 1.51 OK
Side1 Margin Mt. 0.90 - 0.92 OK
Side2 Margin Mt. 0.90 - 0.93 OK

     Building Related Details
Name Description Unit Reqd Perm Proposed Status
A (NEZAMI) Height Mt. 8.91 6.32 OK
A (NEZAMI) First Floor - Height Mt. 2.75 - 3.16 OK
First Floor - Clear Height Mt. 2.75 - 3.05 OK
First Floor - Beam Clear Height Mt. 2.40 - 2.85 OK
Ground Floor - Height Mt. 2.75 - 3.16 OK
Ground Floor - Clear Height Mt. 2.75 - 3.05 OK
Ground Floor - Beam Clear Height Mt. 2.40 - 2.85 OK
A (NEZAMI) Terrace Floor - Height Mt. 1.00 1.20 1.01 OK
A (NEZAMI) No. of Floors No. G + 2 2 OK
No. of Tenements No. - 1 OK
GROUND FLOOR PLAN Staircase -3FL - Flight Width Mt. 0.750 0.850 OK
Staircase -3FL - Tread Width Mt. 0.225 0.254 OK
Staircase -3FL - Riser Height Mt. 0.200 0.113 OK
Staircase -3FL - Riser No. On Flight No. - 7 OK
Staircase -3FL - Cabin Ht. Mt. - - - OK
FIRST FLOOR PLAN Staircase -3FL - Flight Width Mt. 0.750 0.850 OK
Staircase -3FL - Tread Width Mt. 0.225 0.254 OK
Staircase -3FL - Riser Height Mt. 0.200 0.113 OK
Staircase -3FL - Riser No. On Flight No. - 7 OK
Staircase -3FL - Cabin Ht. Mt. - - - OK
TERRACE FLOOR PLAN Staircase -3FL - Flight Width Mt. - 0.850 OK
Staircase -3FL - Tread Width Mt. - 0.254 OK
Staircase -3FL - Riser Height Mt. - - OK
Staircase -3FL - Riser No. On Flight No. - - OK
Staircase -3FL - Cabin Ht. Mt. 2.100 - 2.769 OK
SUMP TANK Area Sq.Mt. - - 5.45 OK
Width Mt. - - 1.66 OK
Depth Mt. - - 3.28 OK
Height Mt. - - - OK
RAIN WATER HARVESTING Area Sq.Mt. - - 5.00 OK
Width Mt. - - 2.00 OK
Depth Mt. - - 2.50 OK
Height Mt. - - - OK
ENT.GATE Area Sq.Mt. - - 0.06 OK
Width Mt. - - 0.02 OK
Depth Mt. - - 2.92 OK
Height Mt. - - - OK
SOLAR HEATING SYSTEM Area Sq.Mt. - - 1.88 OK
Width Mt. - - 1.17 OK
Depth Mt. - - 1.60 OK
Height Mt. - - - OK
A (NEZAMI) GROUND FLOOR PLAN - PORTICO - Width Mt. 1000000.00 2.24 OK
   
    All Rooms are as per Rule in Room Checking




[-] Rules
Topic Rule
Plot Level
Plot Area No rule provided for Min. Plot size for proposed Use
Plot Width No rule provided for Min. Plot size for proposed Use
Plot Depth No rule provided for Min. Plot size for proposed Use
Access Width The minimum width of abutting road for any Building shall be with respect to Length of Road {As per Rule No. 34 Table No.6}
Plot Frontage No rule provided for Min. Plot size for proposed Use
FAR Area (1) In Old Area, for Residential Building on abutting roadwidth 3.60 (12 ft.) to 4.80 mt., the Floor Area Ratio-FAR shall be 1.5 {As per Rule No.39, Table 15}
(2) For this Authority, No Max. permissible FAR has been provided {As per Annexure III}
Consumed FAR (1) In Old Area, for Residential Building on abutting roadwidth 3.60 (12 ft.) to 4.80 mt., the Floor Area Ratio-FAR shall be 1.5 {As per Rule No.39, Table 15}
(2) For this Authority, No Max. permissible FAR has been provided {As per Annexure III}
Common Plot Area In every building area, at least 5% of the land shall be covered by plantation (tree cover). {As per Rule No.33}
Common Plot ; ;
Tree Number 2-4 Trees shall be required for the Plot area upto 250.0 sq.mt. (As per Rule No. 20.1.6)
Margin Rule For Non-highrise Residential Building upto 10.0 mt. Ht. having Plot Depth 10-15 mt. and Plot width 10-15 mt., Margin required in Front shall be 2.0 mt., Rear 1.5 mt. and 0.9 mt. shall be provided on both side. {As per Rule No. 36 (Table 8 & 9)}
Building Level
Building Height For old area, on Road width 3.6-4.8 mt., Permissible height shall in no case exceed(1.5 times the width oftheroadonwhichtheplot abuts) + Road widening + the front setback or 10.0 mt. {As per Rule No. 39.1 Table 15}
Floor Height (1) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
(2) The height of all rooms for human habitation shall not be less than 2.75 m measured from the surface of the floor to the lowest point of the ceiling (bottom of slab){As per Rule No.42.2.1}
Parapet Height Parapet walls and handrails provided on the edges of roof terraces, balcony, verandah, etc shall not be less than 1.0 m and not more than 1.2 m in height from the finished floor level {As per Rule No. 42.5}
Floor Number For old area location,on Road width 3.6-4.8 mt. only G+2 floors shall be allowed {As per Rule No. 39.1 Table 15}
StairCase (1) Width of Winding staircase shall be mini. 0.75 mt.,Maximum rise 0.20 mt. & Minimum tread 0.225 mt. {As per Rule No. 83.18}
(2) ; No Rule Defined
(3) Width of Winding staircase shall be mini. 0.75 mt.,Maximum rise 0.20 mt. & Minimum tread 0.225 mt. & Cabin height 2.1 mt {As per Rule No. 83.18}
(4) ; No Rule Defined
Arch Projection No need to check
Plot / Building Level
Accessory Use (1) -
(2) No need to check distance from Building SUMP TANK
(3) The dimension of recharging pits/trenches shall be at least 6 cubic meters for every 100 Sq. m. of roof area
(4) No need to check distance from Building RAIN WATER HARVESTING
(5) No need to check distance from Building ENT.GATE
(6) -
(7) No need to check distance from Building SOLAR HEATING SYSTEM
Building Level (Rooms)